Coconote
AI notes
AI voice & video notes
Export note
Try for free
PMP Exam Question Practice Summary
Dec 11, 2024
PMP Question Practice Lecture Notes
Overview
Purpose: Prepare for the PMP exam by practicing 5 questions daily
Approach: Solve questions together for a hands-on learning experience
Question 1: Outsourcing a Product Component
Scenario
: Part of a project cannot be completed internally, decision to outsource with a bonus for completion in 2 months.
Contract Types Discussed
:
Cost plus fixed fee
Fixed price with economic adjustments
Time and materials
Fixed price with incentive
Answer
: Fixed price with incentive fee
Allows buyer to allocate incentive based on schedule, cost, or quality metrics.
Question 2: Scheduling Network Diagram
Scenario
: Created a schedule network diagram with durations, early start, and finish dates.
Next Step
: Perform a backward pass noting late start and finish dates.
Answers Discussed
:
Performing a forward pass
Performing a backward pass
Breaking down scope into smaller work packages
Noting float and positions of each activity
Answer
: Perform a backward pass
Calculates late start and finish, helps determine project schedule float.
Question 3: Outsourcing with Low Risk
Scenario
: Project sponsor wants to minimize organizational risk in outsourcing development.
Contract Types Discussed
:
Cost plus fixed fee
Time and materials
Firm fixed price
Cost plus incentive fee
Answer
: Firm fixed price
Least risky for buyer, total costs are predetermined and scope clearly defined.
Question 4: Work Authorization System
Scenario
: Distributing work to team using the work authorization system.
System Functions
:
Manages timing and sequence of activities
Authorizes activities
Answers Discussed
:
Tracking and managing defects
Identifying resources needed
Comparing actual work against baselines
Answer
: Defines how work will be authorized and done in the correct sequence.
Question 5: Change in Project Requirements
Scenario
: Stakeholder requests stage enlargement in a project, not originally planned.
Process Steps
:
Do not start work immediately
Do not update baselines without approval
Analyze impact on cost, schedule, and scope
Submit change request to change control board
Answer
: Analyze impact and submit change request
Assess impact before raising a change request; update baselines post-approval.
Conclusion
Encouragement to continue practicing and studying daily for the PMP exam.
Positive reinforcement and belief in the ability to pass the exam.
📄
Full transcript