Overview
Comparison between perfect tender and substantial performance standards in contract performance.
Focus on the dominance of the substantial performance test in American contract law.
Key Case: Jacob & Youngs v. Kent (1921)
Parties
: Construction of a residence by Mr. George Edward Kent.
Contract Specification
: Required use of Redding brand pipe.
Actual Installation
: Cohoes brand pipe was used.
Legal Issue
: Whether the homeowner could withhold remaining payment due to this deviation.
Judge Cardozo's Opinion
Intent
: The omission of Redding pipe was not fraudulent or willful, rather an oversight.
Comparison
: Redding and Cohoes pipes were identical visually, distinguished only by manufacturer marking.
Finding
: The defect was deemed insignificant in relation to the overall project.
Legal Principles
Substantial Performance
: Minor, innocent omissions can be atoned by allowance of resulting damages, avoiding forfeiture.
Material Breach
: Breach that is significant enough to release the other party from obligations.
Promises and Conditions
: Some promises in a contract are not conditions that free obligations if breached.
Justice and Intention
: Evaluating whether promises are important or trivial based on justice and presumed intention.
Outcome of Jacob & Youngs v. Kent
Not a material breach, as Cohoes pipe met the quality standards expected.
Emphasized practical adaptation over rigid logic in legal doctrine.
Comparative Case: O.W. Grun Roofing v. Cope (Texas, 1975)
Contractor Obligation
: Install roof with russet glow (uniform color) shingles.
Issue
: Installed shingles did not match in color, affecting visual appearance.
Court's Analysis
Good Faith
: Contractor must intend to comply with the contract.
Defects
: Must not be pervasive or deviate from general plan.
Purpose
: Deviation shouldn't prevent achieving the contract's purpose.
Visual Role
: Roofing has a visual component unlike pipe installation.
Outcome
Contractor failed to achieve substantial performance due to visual mismatch of shingles.
Contractor liable for damages, as substantial performance was not achieved.
Consistency Between Cases
Different facts lead to different results; substantial performance is fact-dependent.
Jacob & Youngs
: Structural quality was met, visual role not significant.
Grun Roofing
: Visual role was crucial, substantial performance not met.
Conclusion
Substantial performance doctrine is nuanced and requires evaluating the importance of contractual promises and their role.