⚙️

Understanding Pre-Commissioning and Commissioning

Apr 17, 2025

Commissioning Process: Pre-Commissioning vs. Commissioning

Overview

  • Commissioning Process: Involves distinct stages with pre-commissioning and commissioning.
  • Importance: Small issues in pre-commissioning can become significant later.

Pre-Commissioning

  • Hand Over: Occurs after mechanical completion, marking the transition from construction to commissioning.
  • Purpose: Confirm no damage during shipping and that on-site tests align with factory tests.

Key Concepts

  • Factory Acceptance Testing (FAT): Testing by the manufacturer before shipping.
  • Site Acceptance Testing (SAT): Field testing by vendor or commissioning team.
  • Site Integration Testing (SIT): Tests equipment as a system in the field.

Mechanical Pre-Commissioning Activities

  • Pipe Flushing: Ensures piping is free of blockages.
  • Leak Testing: Checks fittings and joints for leaks.
  • Pressure Testing: Confirms piping can maintain pressure.
  • Verification of Rotational Equipment: Ensures mechanical balance and no excessive vibration.
  • HVAC Testing: Balances airflow, ductwork, and controls.

Electrical Pre-Commissioning Activities

  • Grounding and Bonding Checks: Measures resistance to ensure integrity.
  • Cold Loop Checks and Mega Checks: Verify cable and conductor terminations and integrity.
  • Hot Loop Checks: Confirm calibration of control loops.
  • AC Phase Checks: Verify electrical phase installation.

Transformer and Electrical Tests

  • Transformer Checks: Includes oil samples, winding resistance, and ratio measurements.
  • Protection Relay Testing: Verifies relay inputs through primary and secondary injections.
  • Interlock Verification: Confirms interlocks function correctly.
  • AC and DC Hypot Tests: Measure dielectric resistance.
  • Battery Discharge Tests: Confirm capacity during charge cycles.

Pre-Commissioning Completion

  • Equipment is tested as standalone items.
  • Known as vendor startup, each piece of equipment is confirmed ready for commissioning.

Commissioning

  • Purpose: Tests equipment together as a system.
  • Example: Chemical dosing skid with integrated components like pumps and controllers.
  • Process: Verifies control of equipment as subsystems and their integration.

Key Differences

  • Pre-Commissioning: Individual tests of equipment.
  • Commissioning: System-level tests to ensure intended plant process.

Importance of Completeness

  • Skipping tests leads to issues, e.g., debris in piping affects flow rates.
  • Proper planning includes all necessary tests to ensure a functional system.

Additional Resources

  • Free mini-course available online.
  • Subscription recommended for updates on commissioning and startup processes.