Jun 11, 2024
Earned Value Management (EVM) is a methodology used to measure project performance against project baselines. It integrates the scope baseline, cost baseline, and schedule baseline to form the performance baseline, aiding the project management team in assessing and measuring project progress and performance.
Cost Variance (CV):
EV - AC
Schedule Variance (SV):
EV - PV
Cost Performance Index (CPI):
EV / AC
Schedule Performance Index (SPI):
EV / PV
Estimate at Completion (EAC):
BAC / CPI
: Work performed at current CPI.AC + (BAC - EV)
: Remainder of project at budgeted rate.AC + (BAC - EV) / (CPI * SPI)
: Considering both CPI and SPI.AC + ETC
: Reevaluation based on forecasted ETC.Estimate to Complete (ETC):
EAC - AC
Variance at Completion (VAC):
BAC - EAC
To Complete Performance Index (TCPI):
(BAC - EV) / (BAC - AC)
: Needed rate to complete within planned budget.(BAC - EV) / (EAC - AC)
: Needed rate to complete within specified value (EAC).Planned Value (PV):
PV = $10,000 (Month 1) + $10,000 (Month 2) + $10,000 (Month 3) = $30,000
Earned Value (EV):
EV = $25,000
Actual Cost (AC):
AC = $31,000
Cost Variance (CV):
CV = EV - AC = $25,000 - $31,000 = -$6,000
Schedule Variance (SV):
SV = EV - PV = $25,000 - $30,000 = -$5,000
Cost Performance Index (CPI):
CPI = EV / AC = $25,000 / $31,000 ≈ 0.80
Schedule Performance Index (SPI):
SPI = EV / PV = $25,000 / $30,000 ≈ 0.83
Estimate at Completion (EAC):
EAC = BAC / CPI = $40,000 / 0.80 = $50,000
EVM provides critical insights by comparing planned baselines to actual progress and performance, helping project managers forecast and adjust accordingly. This can involve monitoring budget utilization, schedule adherence, and future project cost predictions.