🔧

Understanding Pre-Commissioning and Commissioning

Apr 17, 2025

Commissioning Process: Pre-Commissioning and Commissioning

Introduction

  • Importance of understanding the commissioning process.
  • Pre-commissioning and commissioning are distinct stages, often confused.

Pre-Commissioning

  • Purpose: Ensures no damage to equipment during shipping/installation; aligns on-site test results with factory results.
  • Mechanical Completion: Marks handover from construction to commissioning teams.
  • Key Testing Terms:
    • Factory Acceptance Testing (FAT): Conducted by the manufacturer before shipping.
    • Site Acceptance Testing (SAT): Conducted on-site either by vendor or commissioning team to confirm no shipping/install damage.
    • Site Integration Testing (SIT): Confirms equipment functions as a system.
  • Mechanical Pre-Commissioning Activities:
    • Pipe flushing, leak testing, pressure testing.
    • Verification of rotational equipment.
    • HVAC testing.
  • Electrical Pre-Commissioning Activities:
    • Grounding and bonding checks.
    • Cold loop and mega checks.
    • Hot loop checks, AC phase checks.
    • Transformer checks and protection relay testing.
    • Interlock verification, AC and DC hipot tests, battery discharge tests.
  • Completion: Ensures all individual equipment is ready for commissioning tests.

Commissioning

  • Purpose: Tests multiple equipment pieces together as a system.
  • Example: Chemical dosing skid system involving pumps, piping, valves, gauges, etc.
  • Process:
    • Each subsystem tested to verify proper function.
    • Integration of subsystems for the project's overall system.
    • Completes with plant startup for intended operation.

Differences Between Pre-Commissioning and Commissioning

  • Pre-Commissioning: Tests equipment individually.
  • Commissioning: Tests equipment as a subsystem.
  • Criticality: Ensure no tests are skipped to avoid future issues.

Conclusion

  • Importance of a well-planned commissioning sequence including all necessary tests.
  • Skipping pre-commissioning tests can lead to significant problems.
  • Encouragement to join further educational resources available online.

Note: For more detailed learning and resources, join the free three-day mini-course available online.