Electrical Service Upgrade Summary

Jul 15, 2025

Summary

  • The meeting covered the full process, key code requirements, and best practices for upgrading an old 100 amp residential electrical service to 200 amps.
  • Detailed steps were given on equipment selection, panel installation, grounding, and bonding, with explanations of code compliance and safety considerations.
  • The discussion included lessons learned, tools used, and rationale for specific installation choices, such as the number of panel circuits and grounding methods.
  • Final installation, labeling, and preparation for inspection were completed, with plans for further minor electrical work and pending final electrical inspection.

Action Items

  • (Pending final inspection) – Contractor: Schedule and complete the final electrical inspection to close out the service upgrade.
  • (Today) – Contractor: Label each circuit breaker on the panel legend as required by code.
  • (Today) – Contractor: Install an exhaust fan in the bathroom.
  • (Today) – Contractor: Replace approximately 15 duplex receptacles.
  • (This week) – Contractor: Fill exterior conduit fitting with duct seal for weather protection.

Service Panel Review and Code Compliance

  • Identified multiple code violations with the previous panel (e.g., wrong breaker types installed, main breaker orientation).
  • Emphasized the importance of using only manufacturer-approved breakers for the panel to ensure safety and proper function.
  • Explained short circuit current ratings and required interrupting capacity for disconnects, especially relevant for inspectors.

Service and Meter Upgrade Process

  • Described installation of a new, larger 200 amp meter enclosure, ensuring it covers the old opening and is watertight.
  • Installation included use of appropriate hubs, irreversible screws, and correct mounting techniques.
  • Overhead service riser and weather head fitted above window per requirements, noting challenges with high riser placement.
  • Adjustments made for depth and height using 2x4s and plywood; tools and work techniques discussed.

Panel Installation and Wiring

  • Selected and installed a surface-mounted 200 amp Cutler Hammer BR panel with a 40 circuit (expandable to 80) capacity.
  • Routed conduit and cabling to maximize code compliance and ease of future expansion.
  • Stressed the importance of using a minimum 40-circuit panel for a 200 amp service for long-term value, especially with growing power demands (e.g., EV chargers, HVAC).

Grounding and Bonding

  • Grounding electrode conductor attached to copper water main within 5 feet of entry, using number two aluminum per code.
  • Two ground rods installed and interconnected using number six copper.
  • Detailed proper bonding techniques between neutral and ground at the main disconnect, avoiding parallel current paths by running four wires to the panel (two hots, neutral, ground).
  • Auxiliary bonding bridge set up for telecommunications or satellite grounding as needed.
  • Completed all exterior and interior grounding to meet inspection and safety standards.

Lessons, Tools, and Safety

  • Discussed tool choices and installation tips, including use of magnetic bits, circular saws, and appropriate extension ladders.
  • Noted lessons learned (e.g., avoid pre-gluing entire riser before measuring, ensure gloves for safety on conductive siding).
  • Praised the value of continuing education for licensed electricians, citing frequent code and practice updates.

Final Steps and Inspection Prep

  • Final checks included securing all connections, centering and fastening the panel, labeling circuits.
  • Necessary weatherproofing and labeling scheduled.
  • Awaiting final inspection to complete the upgrade.

Decisions

  • Chose a 40-circuit (expandable to 80) 200 amp panel for long-term capacity — Ensures future-proofing for increased electrical load, electric vehicles, and modern appliances, offering better value and code compliance than a 20-circuit panel.
  • Maintained original grounding method (jumper on water main) and left old clamps in place — Rationale: Minimize risk of leaks or interruptions to plumbing during upgrade.

Open Questions / Follow-Ups

  • Clarification pending from PSNG inspector regarding meter main acceptance for future projects.
  • Confirm if additional auxiliary grounding for telecom/satellite is required on this installation.
  • Ensure pending final electrical inspection is scheduled and passed.