How to Create a Gantt Chart in Microsoft Project
Overview
- Objective: Learn to create a Gantt chart to visualize tasks, critical paths, and tracking progress in Microsoft Project.
- Resource: Free exercise file available at AlvinThePM.com (Exercise 3).
- Steps Covered:
- Setting up a new project
- Automatically scheduling tasks
- Adding tasks
- Linking tasks and predecessors
- Visualizing critical path
- Setting and visualizing baseline
- Updating progress
- Exporting Gantt chart
Setting Up a New Project
- Start a new project: Open Microsoft Project and start a blank project.
- Auto schedule tasks: Ensure tasks are auto scheduled based on dependencies, resources, and calendar.
- Navigate to the bottom screen, select
new tasks manually scheduled âž” auto scheduled.
Adding Tasks
- Create tasks for different project phases (Example: Home construction with phases - Plans & Permits, Contractor Agreements, Foundation, Framing).
- Adding Milestones: Add milestones below each phase to mark significant achievements.
Linking Tasks
- Sequence of Tasks: Link tasks together in large sequences.
- Using Shortcuts: Use the Chain Button in Task Tab to link tasks.
- Setting Predecessors: Establish correct predecessors to form a logical sequence of tasks.
- Example: Research subcontractors can only start after home plans are developed.
- Updating Durations: Adjust durations to reflect realistic estimates.
- Milestones should have 0 days of duration.
Visualizing the Gantt Chart
- View the entire project Gantt chart:
- Highlight Critical Path: Critical tasks highlighted in red.
- Gantt chart format âž” Critical Tasks (bar styles group).
- Identify Non-Critical Tasks: Tasks not on the critical path will retain original color.
Baseline and Tracking
- Set Project Baseline: Once schedule is established, set it in Microsoft Project.
- Project tab âž” Set Baseline (Schedule group) âž” Set Baseline
- Switch to Tracking Gantt: To see actual percent completion against baseline.
- On left side âž” Gantt Chart âž” Right Click âž” Tracking Gantt
- Dark Gray Bars: Represent plan baselines; Blue/red bars show actual progress.
Updating Progress
- Establish Status Date: Set a specific date to reflect latest project progress.
- Project tab âž” Status Date (Status group)
- Switch Table Mode: From entry to tracking to update tasks' progress.
- Select all tasks âž” right-click âž” Tracking
- Input Actual Durations and Percent Completion: Update duration and mark completion status.
- Example: Develop Home Plans task duration adjusted from 45 to 50 days due to delay.
- Impact on Critical Path: Gantt chart will automatically show how delays affect the critical path.
Exporting Gantt Chart
- Copying Gantt Chart: Export to PowerPoint by switching modes.
- Table Mode âž” Entry âž” Copy Picture âž” Paste in PowerPoint
Pro Tips
- Adding Milestones: Easily highlight key accomplishments.
- Set Baseline: Ensure to set a baseline after project plan is validated.
- Visual Indicators: Use color codes effectively to distinguish task statuses.
- Regular Updates: Keep progress updated for accurate tracking and decision making.
Closing Remarks
- Exercise File: Available for free at AlvinThePM.com (Exercise 3).
- Further Learning: Follow-up video to master Microsoft Project.
Note: Smash the like button and share if you found the video helpful!