Question 1: Reporting Cost Variance

  • Scenario: Found a cost variance of $40,866 in the project.
  • Question: What type of report is needed?
    • Options:
      • Progress report
      • Exception report (Chosen)
      • Forecasting report
      • Trends report
  • Explanation:
    • Exception Report: Used for reporting variances in project cost/schedule/quality.
    • Progress Report: Describes current progress.
    • Forecasting Report: Predicts future performance.
    • Trends Report: Projects trends over a period of time.

Question 2: Tools and Techniques

  • Scenario: Delphi technique, sensitivity analysis, and Monte Carlo analysis.
  • Question: Used as part of which project task?
    • Options:
      • Expert judgment
      • Reserve analysis
      • Schedule compression
      • Quantitative risk assessment (Chosen)
  • Explanation:
    • Techniques related to quantitative risk analysis and financial risk analysis.
    • Methods for determining quantitative probability include interviewing, historical records, sensitivity analysis, decision trees, etc.

Question 3: Risk Management Documentation

  • Scenario: Identifying risks for a project.
  • Question: What document maintains and records information about risks?
    • Options:
      • Risk register (Chosen)
      • Project management plan
      • Tornado diagram
      • Prompt lists
  • Explanation:
    • Risk Register: Document for maintaining and recording identified risks and responses.

Question 4: Risk Analysis Process

  • Scenario: Ranking risks by assessing probability and impact.
  • Question: What is this process called?
    • Options:
      • Deep dive analysis
      • Subjective risk analysis
      • Quantitative risk analysis
      • Qualitative risk analysis (Chosen)
  • Explanation:
    • Qualitative Risk Analysis: Prioritizing risks into categories by assessing probability and impact using a scale (e.g., 1-5).

Question 5: Information Gathering Techniques

  • Scenario: Brainstorming to prepare a list of risks.
  • Question: Which is not a type of information gathering technique?
    • Options:
      • Brainstorming
      • Delphi
      • Interviewing
      • Sensitivity analysis (Chosen)
  • Explanation:
    • Sensitivity Analysis: Not an information gathering technique, related to risk impact assessment.
    • Delphi Technique: Involves rounds of voting for narrowing down options.