PRINCE2 Mock Exam Review and Tips
Aug 6, 2024
PRINCE2 Mock Foundation Exam Review
Exam Information
Closed book exam
Duration: 60 minutes
60 questions (1 minute per question)
Passing score: 60% (36 out of 60)
Format: Multiple choice (1 question, 4 possible answers, only one correct answer)
No trick questions
Exam Tips
Do not spend too much time on one question
Move on if you have difficulties
Time management is crucial
Sample Paper 1 Review
Question 1: Project Context
Right Answer:
A
Explanation:
Understanding the environment where the project operates is key for applying principles correctly.
Question 2: Characteristics of a Project
Right Answer:
C
Explanation:
Projects are unique and different from day-to-day operations.
Question 3: Premature Project Closure
Right Answer:
D
Explanation:
Ensuring continued business justification due to changes in the external environment.
Question 4: Defined Roles and Responsibilities
Right Answer:
D
Explanation:
Suppliers can be external stakeholders; project teams include both internal and external partners.
Question 5: Tolerances and Management
Right Answer:
A
Explanation:
Management by exception; tolerances set to manage without interference unless exceeded.
Question 6: Continued Business Justification
Right Answer:
B
Explanation:
Ensures the project remains desirable, viable, and achievable.
Question 7: Effective Project Management Principles
Right Answer:
A
Explanation:
Principles allow project teams to decide how to apply the method on each project.
Question 8: Leadership in Projects
Right Answer:
A
Explanation:
Best done through collaboration across the project ecosystem.
Question 9: Co-creation
Right Answer:
A
Explanation:
Involves working with key influencers for agreed ways of working.
Question 10: Not an Aspect of Leadership
Right Answer:
A
Explanation:
Instructing task execution is management, not leadership.
Question 11: Leading Across Organizational Boundaries
Right Answer:
B
Explanation:
Integrating new products into business areas likely involves people outside the project team.
Question 12: Importance of Change Management
Right Answer:
A
Explanation:
Helps stakeholders understand impacted organizational areas.
Question 13: Capabilities and Competencies
Right Answer:
B
Explanation:
Team performance varies with team structure.
Question 14: Change Management Approach
Right Answer:
C
Explanation:
Defines future business operations to meet project objectives.
Question 15: Learning from Experience
Right Answer:
A
Explanation:
Workshops to share new ways of working align with learning from experience.
Question 16: Project Scope and Time Scale Commitment
Right Answer:
C
Explanation:
Project initiation document includes scope, time scale, and project plan.
Question 17: Business Case Practice
Right Answer:
A
Explanation:
Enables the executive to decide on project continuation.
Question 18: Progress Justification
Right Answer:
D
Explanation:
Project brief and business case provide necessary information to justify progress.
Question 19: Business Objective
Right Answer:
A
Explanation:
Demonstrates progress in relation to the organization's strategy.
Question 20: Capturing Environmental Targets
Right Answer:
B
Explanation:
Should be captured as sustainability tolerance.
Question 21: Risk Impact on Business Case
Right Answer:
B
Explanation:
Impact assessed during
📄